Performance statistics July–September 2016: Preliminary assessment applications
During this quarter:
- 99 per cent were completed within the 30 day timeframe
- 564 were received
- 654 were processed
- 97 per cent went into evaluation.
Workload and performance preliminary assessment July–September 2016
Application type | Received | Completed | Refused | Withdrawn | Within timeframe (%) |
---|---|---|---|---|---|
Pesticides | 252 | 271 | 4 | 0 | 100 |
Veterinary medicines | 93 | 112 | 5 | 6 | 100 |
Sub total | 345 | 383 | 9(2.3%) | 6(1.5%) | 100 |
Permits | 94 | 107 | 0 | 1 | 100 |
Actives | 125 | 164 | 0 | 0 | 99 |
Total | 564 | 654 | 9(1.4%) | 7(1.1%) | 99 |
Background
Preliminary assessment?is an administrative check of all applications received to ensure the information necessary to proceed to a full evaluation is present.
The timeframe for preliminary assessment 30 days from receipt.